Bupa Health Care Swimming pool & spa (Oxford)

We were called to a Bupa healthcare nursing home to investigate heat loss in the swimming pool. After a thorough assessment, we found that the air handling units were drawing heat from the pool’s heat exchanger due to inadequate flow rates.

To resolve this, we designed and implemented a solution, upgrading the primary flow and return pipework to 54mm and installing two 600-litre buffer vessels. We also added auxiliary pumps and upgraded the flow and return connections to the pool, spa, and air handling units to 42mm, ensuring improved efficiency and heat retention.

Mosque

This project takes place at a newly constructed mosque in Sheffield, where the entire ground floor is heated through an underfloor heating system. The heating is powered by two 40kW Ideal Evo Max boilers, providing a combined output of 80kW. To distribute the heating effectively, we designed and installed a custom manifold using 54mm copper pipe, which branches off into multiple circuits to ensure even heat distribution throughout the space.

In addition to supplying the underfloor heating system, these boilers also serve a 600L unvented hot water cylinder, ensuring a reliable and efficient hot water supply for the facility. The system has been carefully designed to maximize performance, efficiency, and longevity.